Work performed last week:
- Removed stumps and debris from the West side of the site
- Installed the gabion baskets (stone wall) in the sediment pond, fine graded, and seeded which completed the installation of the storm water basin
- Poured the slab-on-grade in Units C and D
- Continued exterior and interior concrete masonry unit walls to scaffold height in Units C and D
- Laid interior concrete masonry unit foundation walls in Food Service
- Continued exterior concrete masonry unit walls to second floor joist bearing in Unit B
- Continued exterior and interior concrete masonry unit walls to scaffold height in Unit A
- Delivered steel lintels and bearing plates, and set bearing plates in Unit B
- Continued under-slab PVC plumbing and electrical in Units B and A
- Continued mechanical and electrical rough-in in the equipment room
- Continued under-slab rough-in for food service equipment
- Continue plumbing and electrical wall rough-in in Units D, C, B and A
Note: Areas D & C are the single story section of the school. That includes the gym, cafeteria, kitchen, music, art and fitness rooms. Areas A & B are the 3-story classroom sections.