Work performed last week:
- Continued clearing trees on the West end of the property
- Connected an 8-inch fire line to the City’s main water line on Ironbound Road
- Completed the storm system to SS#2-4 at the corner of Cooley Field
- Grouted the exterior concrete masonry unit walls to the first floor lintel height in Unit B and to scaffold height in Unit A
- Continued exterior concrete masonry unit walls in Unit A and B
- Prepared and poured the slab-on-grade in the Gymnasium
- Continued under-slab and in-wall plumbing and electrical rough-in in Units B, C and D
- Completed the underground secondary electrical feed conduit in the mechanical area
- Completed the sprinkler access slab in Fire Pump room
Note: Areas D & C are the single story section of the school. That includes the gym, cafeteria, kitchen, music, art and fitness rooms. Areas A & B are the 3-story classroom sections.