2/17/17 Construction Update

$
0
0

Work performed last week:

  • Continued clearing trees on the West end of the property
  • Connected an 8-inch fire line to the City’s main water line on Ironbound Road
  • Completed the storm system to SS#2-4 at the corner of Cooley Field
  • Grouted the exterior concrete masonry unit walls to the first floor lintel height in Unit B and to scaffold height in Unit A
  • Continued exterior concrete masonry unit walls in Unit A and B
  • Prepared and poured the slab-on-grade in the Gymnasium
  • Continued under-slab and in-wall plumbing and electrical rough-in in Units B, C and D
  • Completed the underground secondary electrical feed conduit in the mechanical area
  • Completed the sprinkler access slab in Fire Pump room

Note: Areas D & C are the single story section of the school. That includes the gym, cafeteria, kitchen, music, art and fitness rooms. Areas A & B are the 3-story classroom sections.

 

 

 

 