2/19/2018 – Construction Update

$
0
0

Work Performed this Week:

  • Continued brickwork on the West and South elevations in Unit C and D
  • Continued interior non-bearing CMU walls throughout
  • Continued adjusting the operable partition wall support steel in Unit B
  • Installed structural steel at the student entrance canopy
  • Installed steel in Stair AS-3
  • Installed railings in Stair BS-1
  • Continued exterior framing in the Auditeria and Food Service parapet
  • Continued installing exterior windows in Unit A1
  • Continued PVC roofing in Units A and C
  • Continued installing framing and cleats for the exterior composite wall panels in Unit B
  • Continued interior framing, hanging gypsum board, sound insulation, and finishing in Units AB3, AB2, and B1
  • Continued priming and painting the walls in Units AB3 and AB2
  • Pulled and connected main electrical feeder wire from the switchgear to the primary electrical panels
  • Continued hanging VAVs and ductwork in Units A, B, C, and D
  • Insulated low and medium pressure ductwork in Units AB3 and AB2
  • Continued domestic water supply piping in Unit B in interior CMU walls
  • Continued steel hydronic piping in Unit C
  • Began installing ceiling grid in Unit B3

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

The post 2/19/2018 – Construction Update appeared first on Williamsburg-James City County Public Schools.