Work Performed this Week:
- Continued brickwork on the West and South elevations in Unit C and D
- Continued chase wall CMU in Unit B
- Continued adjusting the operable partition wall support steel in Unit B
- Installed steel framing in Stair AS-3
- Installed railings in Stair BS-1
- Continued exterior framing in the Auditeria and Food Service parapet
- Continued installing exterior windows in Unit B
- Continued installing the curtainwall framing in Unit B
- Continued PVC roofing in Unit A above the research commons
- Continued installing framing and cleats for the exterior composite wall panels in Unit C
- Continued interior framing, hanging gypsum board, sound insulation, and finishing in Units AB2 and B1
- Continued priming and painting the walls in Units AB3 and AB2
- Continued wall and above ceiling rough-in and pulling wire in Units A and B
- Set rooftop air handling units on the roofs of Units C and D
- Continued hanging VAVs and ductwork in Units A, B, C, and D
- Insulated low pressure ductwork in Units AB3 and AB2
- Continued domestic water supply piping in Unit B in interior CMU walls
- Continued steel hydronic piping in Unit C
Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.