2/12/2018 – Construction Update

$
0
0

Work Performed this Week:

  • Continued brickwork on the West and South elevations in Unit C and D
  • Continued chase wall CMU in Unit B
  • Continued adjusting the operable partition wall support steel in Unit B
  • Installed steel framing in Stair AS-3
  • Installed railings in Stair BS-1
  • Continued exterior framing in the Auditeria and Food Service parapet
  • Continued installing exterior windows in Unit B
  • Continued installing the curtainwall framing in Unit B
  • Continued PVC roofing in Unit A above the research commons
  • Continued installing framing and cleats for the exterior composite wall panels in Unit C
  • Continued interior framing, hanging gypsum board, sound insulation, and finishing in Units AB2 and B1
  • Continued priming and painting the walls in Units AB3 and AB2
  • Continued wall and above ceiling rough-in and pulling wire in Units A and B
  • Set rooftop air handling units on the roofs of Units C and D
  • Continued hanging VAVs and ductwork in Units A, B, C, and D
  • Insulated low pressure ductwork in Units AB3 and AB2
  • Continued domestic water supply piping in Unit B in interior CMU walls
  • Continued steel hydronic piping in Unit C

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

The post 2/12/2018 – Construction Update appeared first on Williamsburg-James City County Public Schools.