Work Performed this Week:
- Poured concrete treads and landings in Stair BS-1
- Continued brickwork on the West and South elevations in Unit C and D
- Continued chase wall CMU in Unit B
- Continued installing the operable partition wall support steel in Unit B
- Continued roof steel above the student entrance and throughout Unit D
- Continued exterior framing in Units A and C along the parapet and high walls
- Continued installing exterior windows in Unit A
- Continued spray polyurethane foam insulation on the exterior walls in Units A, B and C
- Continued PVC roofing in Unit D
- Continued installing wall clips and framing for the exterior composite wall panels in Units A and C
- Continued priming and painting the framed walls in Unit B3
- Continued interior framing, hanging gypsum board, sound insulation, and finishing in Unit B2
- Continued wall and above ceiling rough-in and pulling wire in Units A and B
- Continued hanging VAVs and ductwork in Units A and B
- Insulated low pressure ductwork in Unit B3
- Continued domestic water supply piping in Unit B
- Continued steel hydronic piping in Unit C
- Pulled low voltage wiring in Unit B3
- Installed and pressurized the Virginia Natural Gas service line
Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.