Work Performed this Week:
- Continued structural steel and roof decking in Unit B
- Began installing roof decking in Unit C locker rooms
- Continued exterior metal framing
- Continued load-bearing masonry in Units A3 and B3
- Started installing sprinkler pipe in Units B2 and A2
- Continued mechanical, electrical, and plumbing wall rough-in as masonry work progressed
- Continued hanging ductwork in Unit C in the gymnasium
- Continued above ceiling domestic water piping in Units B1 and A1
- Chillers were delivered and set in the mechanical room
- Set mechanical equipment curbs on the mechanical room roof
- Continued electrical above ceiling rough-in in Units B2 and A2
- Continued rough-in in the main electrical room in Unit C
- Continued grading the bus loop subgrade
Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.