Work Performed this Week:
- Continued structural steel, joists, and decking in Unit A3
- Started load-bearing masonry in Unit B3
- Continued mechanical, electrical, and plumbing wall rough-in as masonry work progresses
- Continued hanging ductwork in Units B1 and A1, and began ductwork in Unit B2
- Resumed chilled water piping in Unit A1
- Poured the elevated deck in Unit B3 and portal slab in Unit B2
- Continued ball field subgrade grading
- Continued foundation brick and masonry flashing in Unit B
- Started installation of the gymnasium roof
- Began rough grading along the access road between the bus loop and Central Office parking lot
Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.