8/11/17 – Construction Update

$
0
0

Work Performed this Week:

  • Continued structural steel, joists, and decking in Unit A3
  • Started load-bearing masonry in Unit B3
  • Continued mechanical, electrical, and plumbing wall rough-in as masonry work progresses
  • Continued hanging ductwork in Units B1 and A1, and began ductwork in Unit B2
  • Resumed chilled water piping in Unit A1
  • Poured the elevated deck in Unit B3 and portal slab in Unit B2
  • Continued ball field subgrade grading
  • Continued foundation brick and masonry flashing in Unit B
  • Started installation of the gymnasium roof
  • Began rough grading along the access road between the bus loop and Central Office parking lot

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.