Work performed last week:
- Excavated and poured exterior column footings for canopies in Unit A
- Continued exterior and interior concrete masonry unit walls on Level 1 to Level 2 joist bearing in Units A and B
- Continued gymnasium concrete masonry unit walls
- Continued in-wall plumbing and electrical rough-in in Units A and B on Level 1
- Completed under-slab and in-wall plumbing and electrical rough-in in the mechanical room and food service area
- Continued slab-on-grade preparation in the mechanical room and food service area
- Delivered structural steel
- Continued storm structures and pipe along Longhill Road
- Continued the fire line from Ironbound Road toward the building
Note: Areas D & C are the single story section of the school. That includes the gym, cafeteria, kitchen, music, art and fitness rooms. Areas A & B are the 3-story classroom sections.