4/21/17 Construction Update

$
0
0

Work performed last week:

  • Excavated and poured exterior column footings for canopies in Unit A
  • Continued exterior and interior concrete masonry unit walls on Level 1 to Level 2 joist bearing in Units A and B
  • Continued gymnasium concrete masonry unit walls
  • Continued in-wall plumbing and electrical rough-in in Units A and B on Level 1
  • Completed under-slab and in-wall plumbing and electrical rough-in in the mechanical room and food service area
  • Continued slab-on-grade preparation in the mechanical room and food service area
  • Delivered structural steel
  • Continued storm structures and pipe along Longhill Road
  • Continued the fire line from Ironbound Road toward the building