Work performed last week:
- Placed asphalt in the fire line connection on Ironbound Road
- Continued slab-on-grade preparation in Units A and B
- Continued footings in Units A and B
- Continue interior foundation walls in Units A and B
- Installed steel lintels and bearing plates in Unit B
- Continued exterior concrete masonry unit walls (the concrete block walls visible in all the photos) in Unit B to four feet above the Level 2 floor line
- Completed under-slab plumbing in Unit C Food Service
- Continued under-slab mechanical and electrical rough-in in the mechanical rooms
- Continued mechanical and electrical wall rough-in in Units A and B on Level 1
Note: Areas D & C are the single story section of the school. That includes the gym, cafeteria, kitchen, music, art and fitness rooms. Areas A & B are the 3-story classroom sections.