Work performed last week:
- Continued footing and concrete masonry unit foundation walls in Units A and B.
- Continued under-slab and in-wall plumbing and electrical rough-in in Units C and D.
- Began in-wall electrical rough-in in Unit B.
- Continued concrete masonry unit walls at the gymnasium and begin concrete masonry unit walls in Unit B.
- Set the elevator sleeve.
- Continue underground storm pipe from the existing structure to the sediment pond near the
home team locker room.
Note: Areas D & C are the single story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections
Photos